Installation instruction
2.1 There are 7 pieces supports in total and every support has specific mark(we marked them with 1.2.3.4.5.6.7 by marking pen),you can install them one by one from the end of chip conveyor to the head, and from the number 1 to number 7).
3.1 Please start from the end two sections which marked A on the flange.. Adjust the space of each section, ensure the distance between each part is approximate 300 mm as the above picture appeared.
3.2 Unfasten the iron wire which connected the lower and upper chain, put the lower chain of two section together first, thread a axis to connect them, then install cotter pin on both sides of axis to fasten.
3.3 Connect the upper chain with the same way.
4.1 After the end two section chain finished which marked A, then can go for the body connect.
4.2 Drag the chain of other side which has not connected to make the chain straight and move the body together, install the sealing strips then coat the sealant.(Because of the sealant belong to prohibited articles, we can not provide it, you can get it from your side)
4.3 Screw the bolt to fasten the body.(see below drawing)
5.Connecting the chain of the head of conveyor.(details you can see from the operating manual)